Our Home

I decided to make a post with the progress on our house. I take a picture of the house the first day of each month and then we will have a finished house at the end. Hopefully it flies by and before we know it we have our finished forever house.

A few years ago, a neighborhood a little south of our house at the time caught our attention. It had a little bigger lots and space and it was quiet and peaceful. We talked about buying a house there and kept our eye out for any that went up for sale in that neighborhood. We went through one- it was a very nice house, but I didn’t love the layout. Ryan loved it, especially the backyard. It was a little out of our budget too. We put a pin in it for awhile. Then when COVID started we decided we wouldn’t mind having a little more space and looked again. Not many houses go up for sale in the neighborhood, there are only a dozen or so houses in the whole neighborhood. We heard that they might be developing more lots behind the houses already there. In December 2021 they put about a dozen more lots up for sale. We had never really planned on building a house but since there were now open lots in the area that we wanted to live we thought it was a good option. So in January 2022 we decided to do it. We then had to pick a lot, find the builder, arrange financing, and decide on the plans we wanted. In May of 2022 we signed the papers and it was time to start building.

The first order of business was to get permits and things in order with the city and county…it took a while. A long while. June. July. August long while. Finally in September the permits and everything were in order and we started digging.

June…July…August
September 2022- Foundation hole dug.
October-Foundation walls poured, backfill on walls, temporary driveway placed.
November 2022-Basement plumbing put in, basement floor poured, walls water proofed, more backfill done.
December 2022-More back fill, garage floors poured, getting staged to frame.

January-February 2023- Framing finally started. Lots of snow, rain, and freezing weather made it go slower then we hoped.

March 2023- finished up framing. Small delay from a roof mishap. Roof started and ready for windows.
April- Roof put on, lower windows installed, framing finished, HVAC and cabinet drawings started.

Inside house pictures from April.

May- rest of windows installed, front porch poured, HVAC, plumbing, and electrical installed, temporary doors installed. Picked out tile and flooring.

June- inspections for plumbing electrical and gas were done so not much happened while we waited on that. They put the piers in for the back deck, and started on insulation once inspections were passed. I picked out some furniture for the living room and decided on tile and lighting.

July-August Inspections, and finishing plumbing and electrical seemed to take FOREVER. There were a few little things done while we waited on that. I think our builders were focused on other things to be honest. It was a very frustrating slow process. Towards the end of August things started picking up again. They put the stucco on the outside and got the house prepped for painting. Doors were hung. I picked out all the tile, stone, floors, paint, plumbing and anything else we needed to decide on while we ‘waited’ for whatever we were waiting for.

September-October Cabinets got installed, outside was painted, deck installed, drywall and mudding done, countertops installed, interior painting done, tile for kitchen and baths done, flooring started. Back patio and part of driveway and sidewalk poured. Found out the masonry was on strike and they can’t get any stone right now so still waiting for stone to be installed.

October-December 2023

Stucco, stone, and painting on the outside was done. Final grading, deck installed, fireplace stone done. There were a lot of things accomplished in November but the hoped for move in date of something in November was a little ambitious. Weather, holidays, and the universe testing my patience, slowed things down enough that we decided to shoot for December. Flooring, touchups, lighting installed, carpet, finish work like doors, hardware and lots of little things you don’t even think about were done. The house was pretty much done shortly after Thanksgiving. At the beginning of December we did an initial walk through and made a list of things that needed to be done, touched up or were missed. They got most of that done and then started the final clean ups. It was the middle of winter so we got temporary occupancy until we have some landscaping in. We told them we would not sod or plant grass in December. The city was cool with that, the loan company was kind of turds about it. It all got figured out and we started to move into our house on December 18, the movers brought the last of everything on December 23rd. Just a little over a week shy of when we decided to start this whole process and picked out lot out in January 2022. It has been a hectic two years. I don’t know if we would do it again😜 but we did it once! We love it and hope it will be a good home for us for a very long time!

Here are some pictures from the last month or so of everything starting to come together.

As I mentioned since it was the middle of winter we couldn’t do much yard work. They had to dig up the back yard about a month after we moved in to replace one of the septic tanks. We were really glad we didn’t have sprinklers and grass already installed. That would have been maddening. My sister Sherri put an awesome plan together for us though to show what we are going to start working on in the spring. It will take a few years but we are thinking something pretty close to this. We have a lot of work ahead of us!

This last picture is the first of many I will take of the sunrise from our deck at our house. That is one of my favorite things about our new house. The sunrise and sunsets are amazing!